NASA managers weighed all options and have decided to continue working toward a Feb. 7 launch with full mission content. A decision was made to select an alternate hose design, assembled from shorter hoses that were previously certified and tested, for use aboard the station as the primary jumper. Also, managers decided on the accelerated development of a redesigned set of hoses, based on the design that failed, for use in the event a problem arises with the new primary design. Discussions were discontinued related to partial activation of the Tranquility module.